How much electricity do AI data centers use?

Data centers of every kind used about 415 terawatt-hours (TWh) of electricity in 2024, roughly 1.5% of the world's total, and the International Energy Agency projects about 945 TWh by 2030, with AI servers driving much of the growth. The strain is local: US data centers used about 4.4% of the country's electricity in 2023 and could reach 6.7% to 12% by 2028. Cisco's Jeetu Patel told Chain of Thought that data centers are now being built where power availability is highest, instead of power being brought to them.

· Chain of Thought

Level 1: How AI works

AI Energy & Data CentersAI Infrastructure

  • 4 episodes
  • 4 guest clips
  • 3 common questions
  • 2 glossary terms

In detail

The global number is small, and it is growing fast

The International Energy Agency estimates that data centers used about 415 TWh of electricity in 2024, about 1.5% of global consumption, and that their use has grown about 12% a year over the last five years. In its Base Case, that figure reaches about 945 TWh by 2030, just under 3% of the world’s electricity. These numbers cover every data center workload: email, streaming, storage and AI.

The AI share shows up in the growth. The agency projects that electricity use by accelerated servers, which it says is mainly driven by AI adoption, grows about 30% a year, compared with 9% for conventional servers. Accelerated servers account for almost half of the projected net increase. The United States and China account for nearly 80% of the growth to 2030. (IEA figures checked October 24, 2026.)

The strain is local

A 3% global share sounds manageable, and on a world scale the agency calls it limited. A data center does not draw from the world grid, though. It draws from one utility’s lines. The Lawrence Berkeley National Laboratory report released by the US Department of Energy puts US data center use at 58 TWh in 2014 and 176 TWh in 2023, about 4.4% of US electricity. It estimates 325 to 580 TWh by 2028, or about 6.7% to 12%.

Supply takes longer than demand. In its executive summary, the IEA notes that new transmission lines can take four to eight years in advanced economies, and that wait times for transformers and cables have doubled in the past three years. Jeetu Patel describes how the industry is responding: instead of pulling power to where a data center is wanted, companies now build data centers where power is available. He expects countries to want their own sovereign data centers as well.

Kyndryl’s Kris Lovejoy works on the same problem from the operator side. She says PJM, the organization that forecasts load for its grid region, comes back every year to say it underestimated the previous year’s demand, always by a double-digit percentage. In her view, newer facilities are efficient, with liquid cooling and recycling; the issue is the number of devices that need power.

Efficiency inside the building is not the main lever

Andy Masley, who fact-checks AI environmental claims, argues that data centers are already heavily energy-optimized, because their operators are highly incentivized to cut energy use. He thinks the useful argument is about whether a given facility should be built and whether the uses of AI are worth the energy. Pressuring companies to shave consumption inside the building matters much less in his view.

Lovejoy points to one inefficiency she sees in practice: power is provisioned into a data center and then goes unused, so the operator files another connection request for more. Better rack planning recovers some of that capacity without a new grid connection.

Separate your prompt from the buildout

The personal question and the grid question have different answers. A single chatbot prompt is a tiny amount of energy, which the explainer on whether using AI is bad for the environment works through with Masley’s comparisons. The data center buildout is where demand, siting and the power mix are decided. Masley makes the same split: once you are talking about data centers, you are talking about the grid, both demand and supply.

The IEA also models the other direction. It estimates that existing AI-led efficiency measures in buildings, if scaled up, could save about 300 TWh of electricity, roughly the annual generation of Australia and New Zealand combined. That is a projection of what is possible, not a measured result.

Where it falls short

Forecasts disagree widely. The LBNL range for 2028 spans 325 to 580 TWh, and the IEA’s 2035 cases run from about 700 to 1,700 TWh depending on efficiency gains and how fast AI is adopted. These headline totals cover all data center workloads; they are not standalone estimates of AI use. When you see a single number for “AI’s electricity use,” check what it counts and which year it projects.

Databricks’ Denny Lee is more concerned about energy limits than inference costs for the next few years: inference will keep getting cheaper, but energy is harder to solve and takes more time. That is a forecast, not a measurement. For hardware choices that change the energy cost per answer, continue with why AI runs on GPUs.

Disclosure: Episode 45 is sponsored by Galileo, the Season 3 presenting sponsor; the thanks is at 0:00. Episode 22 was sponsored by Galileo, and Conor notes Databricks’ investment in Galileo at 13:44. Conor worked at Galileo at the time.

Data center electricity: a small global share, a fast local squeeze Left: global data center electricity use, about 415 terawatt-hours in 2024 (about 1.5% of world electricity) and about 945 terawatt-hours projected for 2030 in the International Energy Agency Base Case (just under 3%). Right: United States data centers, 176 terawatt-hours in 2023 (about 4.4% of US electricity) and a projected 325 to 580 terawatt-hours in 2028 (about 6.7% to 12%), from the Lawrence Berkeley National Laboratory report released by the US Department of Energy. Bottom: the constraint is the grid connection. New transmission lines can take four to eight years, and Cisco's Jeetu Patel says data centers are now built where the power is. Small worldwide, heavy where it lands Electricity used by all data centers, AI included. Future figures are projections, not measurements. WORLD · IEA BASE CASE 415 TWh ~945 TWh 2024 · ~1.5% 2030 · just under 3% UNITED STATES · LBNL / DOE 176 TWh 325–580 TWh 2023 · ~4.4% 2028 · ~6.7% to 12% THE CONSTRAINT IS THE GRID CONNECTION New transmission lines: 4–8 years in advanced economies, per the IEA Built where the power is Jeetu Patel, episode 44: sites follow power, not the reverse Sources: IEA, Energy and AI (2025); LBNL report released by the US Department of Energy (Dec. 2024). Checked Oct. 24, 2026.
All data centers, AI included. Figures from the IEA’s Energy and AI report and the LBNL report released by the US Department of Energy; the siting point is Jeetu Patel’s, from episode 44. Download the image

Hear it from the guest

“Data centers are getting built where the power availability is the highest.”
“It's just that there are a lot more devices, right? It's just, it's a question of scale.”
Watch on YouTube
“Data centers are definitely at least more of a conversation about now we're talking at the general grid level and what's affecting the grid both on the demand and the supply side.”
Andy Masley, Effective Altruism DC EP 45 · around 44:30 · read the transcript
“Energy is harder to solve. It takes more time.”

Quotes lightly edited to remove filler words.

Go deeper

Common questions

What share of US electricity goes to data centers?
About 4.4% in 2023, or 176 TWh, according to the Lawrence Berkeley National Laboratory report published by the US Department of Energy in December 2024. The same report projects 325 to 580 TWh by 2028, which would be roughly 6.7% to 12% of US electricity.
Will data center electricity use double by 2030?
In the International Energy Agency's Base Case, yes: from about 415 TWh in 2024 to about 945 TWh in 2030, just under 3% of global electricity. The agency's scenarios for 2035 range from about 700 to 1,700 TWh, so treat any single forecast as one estimate.
Does one chatbot prompt use a lot of electricity?
No. The aggregate buildout is the part that matters for the grid. Andy Masley's comparisons for a single prompt, and the errors in widely shared figures, are covered in the explainer on whether using AI is bad for the environment.